THE CORPORATIONS LAW

CHAPTER 7 - SECURITIES

PART 7.10 - THE NATIONAL GUARANTEE FUND

Division 9 - General provisions relating to claims

SECTION 976   PROCEEDINGS IN THE COURT  

976(1)  [Where SEGC disallows claim]  

Where SEGC has disallowed a claim, the claimant may, within 3 months after notice of the disallowance has been served on the claimant, or on the claimant's solicitor, in accordance with section 975, bring proceedings in the Court to establish the claim.

976(2)  [Claim neither allowed nor disallowed]  

Where, as at the end of a reasonable period after a claim was made, SEGC has neither allowed nor disallowed the claim, the claimant may bring proceedings in the Court to establish the claim.


 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.