MINERALS RESOURCE RENT TAX ACT 2012 (REPEALED)

CHAPTER 4 - SPECIALIST LIABILITY RULES  

PART 4-3 - ADJUSTING MRRT LIABILITIES  

Division 160 - Adjustments to revenue and expenditure of project interests  

Operative provisions  

SECTION 160-15   EFFECT OF MINING ADJUSTMENTS ON MINING REVENUE, MINING EXPENDITURE ETC.  

160-15(1)    
The table has effect for the * MRRT year in which the mining adjustment arises:


Effect of mining adjustments
Item Column 1
If the original amount was an amount included (or not included) in :
Column 2
and if the circumstance or event was taken into account in working out the original amount, it would :
Column 3
The mining adjustment is included in :
1 * mining revenue for a mining project interest increase mining revenue for that interest
2 * mining revenue for a mining project interest decrease * mining expenditure for that interest
3 * mining expenditure for a mining project interest increase mining expenditure for that interest
4 * mining expenditure for a mining project interest decrease * mining revenue for that interest
5 * pre-mining revenue for a * pre-mining project interest increase pre-mining revenue for that interest
6 * pre-mining revenue for a * pre-mining project interest decrease * pre-mining expenditure for that interest
7 * pre-mining expenditure for a * pre-mining project interest increase pre-mining expenditure for that interest
8 * pre-mining expenditure for a * pre-mining project interest decrease * pre-mining revenue for that interest

Example 1:

In MRRT year 1, a miner incurs expenditure of $ 100 million on some machinery that the miner expects to use to the extent of 40 % in the upstream mining operations of a mining project interest for each of 5 years, after which the machinery will be sold. On this basis, $ 40 million is included in the miner ' s mining expenditure for the mining project interest for MRRT year 1.

In MRRT year 2, the miner ' s use of the machinery in those operations increases to 50 % , and the miner expects that extent of use to continue for the rest of the 5 years. As a result, the extent to which the expenditure relates to the interest increases to 48 % . Accordingly, a further $ 8 million is included in the miner ' s mining expenditure for the interest for MRRT year 2.

Example 2:

In MRRT year 1, the miner incurs expenditure of $ 100 million on some machinery, which the miner expects to use for 4 years, but does not expect to use to any extent in the upstream mining operations of a mining project interest. Therefore, none of the expenditure is included in the miner ' s mining expenditure for the mining project interest for MRRT year 1.

In MRRT year 3, the miner starts to use the machinery to the extent of 10 % in those operations, and expects that extent of use to continue until the end of 4 years. As a result, an amount of $ 5 million is included in the miner ' s mining expenditure for the mining project interest for MRRT year 3: 10 % × 2/4 × $ 100 million.


160-15(2)    
However, for the purposes of items 5, 6, 7 and 8 of the table, if a mining project interest that * originates from the * pre-mining project interest exists, the mining adjustment is instead included:


(a) in the circumstances specified in item 5 or 8 of the table - in the * mining revenue of the mining project interest; or


(b) in the circumstances specified in item 6 or 7 of the table - in the * mining expenditure of the mining project interest.

160-15(3)    
If this Division has given rise to a mining adjustment in relation to the original amount then, in working out whether a later event or circumstance gives rise to an adjustment under this Division in relation to the original amount, this Division has effect as if:


(a) the adjustment mentioned in column 3 of the table in subsection (1) had not been made; and


(b) the original amount had instead been increased or decreased (as the case requires) as mentioned in column 2 of that table by the amount of the adjustment.

160-15(4)    
If, apart from this subsection, the original amount:


(a) would be included in the * mining revenue or * mining expenditure for a mining project interest, or in the * pre-mining revenue or * pre-mining expenditure for a * pre-mining project interest ; and


(b) under paragraph (3)(b), would be a negative amount;

the original amount is instead taken to be a positive amount included in the mining expenditure or mining revenue of the mining project interest, or in the pre-mining expenditure or pre-mining revenue of the pre-mining project interest, as the case requires.


160-15(5)    
If this Division has given rise to a mining adjustment in relation to an original amount of * mining expenditure to which subsection 30-40(2) applies, that subsection has effect as if:


(a) the adjustment mentioned in column 3 of the table in subsection (1) of this section had not been made; and


(b) the original amount had instead been increased or decreased (as the case requires) as mentioned in column 2 of that table by the amount of the adjustment.


160-15(6)    
If this Division has given rise to a mining adjustment in relation to an original amount of * pre-mining expenditure to which paragraph 70-40(2)(b) applies, and to which subsection 30-40(2) would have applied if the pre-mining expenditure had been mining expenditure for a mining project interest, that paragraph has effect as if:


(a) the adjustment mentioned in column 3 of the table in subsection (1) of this section had not been made; and


(b) the original amount had instead been increased or decreased (as the case requires) as mentioned in column 2 of that table by the amount of the adjustment.



 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.