MINERALS RESOURCE RENT TAX ACT 2012 (REPEALED)

CHAPTER 2 - GENERAL LIABILITY RULES  

PART 2-3 - MINING PROFITS  

Division 30 - Mining revenue  

Subdivision 30-B - Revenue from supply, export or use of taxable resources  

SECTION 30-35  

30-35   WHEN SUPPLIES ARE MADE  
Treat the time when a miner makes a * supply for the purposes of this Act as the earliest of the following:


(a) when consideration for the supply is received or becomes receivable;


(b) when what is being supplied is delivered;


(c) when ownership of what is being supplied passes.


 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.