4(1)    
An integrated GTL operation exists if there is an operation (the overall operation ) in which:


(a) petroleum is, or will be, recovered from a petroleum project; and


(b) sales gas is, or will be, produced from some or all of the petroleum; and


(c) some or all of the sales gas is, or will be, processed into a liquefied product.


4(2)    
The project natural gas of the integrated GTL operation is the petroleum (natural gas) mentioned in paragraph (1)(a) from which sales gas will be produced and processed into liquefied product within the overall operation (including any of that natural gas that is used in that production and processing).

4(3)    
The project sales gas of the integrated GTL operation is the sales gas mentioned in paragraph (1)(b) that will be processed into liquefied product within the overall operation (including any of that sales gas that is used in that processing).

4(4)    
The liquefied product mentioned in paragraph (1)(c) is project liquid of the integrated GTL operation.

4(5)    
The project natural gas, project sales gas and project liquid are project product of the integrated GTL operation.

4(6)    
The production year for the integrated GTL operation is:


(a) if an election has been made in relation to the integrated GTL operation under regulation 43 - the 2012-13 year of tax; and


(b) otherwise - the year of tax in which processing first occurred.


4(7)    
The 31 December of the production year is the production date for the integrated GTL operation.

4(8)    
The period beginning with the production year and ending with the year of tax in which project sales gas is last processed into project liquid is the operating life of the integrated GTL operation.

4(9)    
If the integrated GTL operation produces a marketable petroleum commodity other than project sales gas, the year of tax in which it is first produced is the MPC production year for the integrated GTL operation.


 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.