PETROLEUM RESOURCE RENT TAX ASSESSMENT REGULATIONS 2005 (REPEALED)

PART 2 - DEFINITION PROVISIONS  

REGULATION 9   ESTIMATED AVERAGE ANNUAL VOLUME OR MASS OF PROJECT NATURAL GAS  

9(1)    
The participants in an integrated operation must give to the Commissioner estimates of:


(a) the operating life of the operation, in years; and


(b) either:


(i) if the participants will measure by volume - the total volume of project natural gas to be recovered during the life of the operation; or

(ii) if the participants will measure by mass - the total mass of project natural gas to be recovered during the life of the operation.

9(2)    
The estimates must be given to the Commissioner:


(a) if an election has been made in relation to the integrated operation under regulation 43 - no later than:


(i) the day on which the participants must give to the Commissioner a starting base return under subclause 22(2) of Schedule 2 to the Act; or

(ii) a later day that the Commissioner allows.


(b) otherwise - in the financial year before the production year.

9(3)    
As soon as practicable after receiving an estimate (including a revised estimate under subregulation (4)) from the participants, the Commissioner must notify them in writing that the Commissioner:


(a) accepts the estimate or revised estimate; or


(b) has substituted an estimate under subregulation (5).

9(4)    
If, from new information, it appears that an estimate notified by the Commissioner is inaccurate, the participants must give to the Commissioner a revised estimate.

9(5)    
If, having regard to relevant information, the Commissioner is not satisfied that an estimate given by the participants for subregulation (1) or (4) is reasonable, the Commissioner may substitute an estimate that the Commissioner is satisfied is reasonable.

9(6)    
For an operation in which natural gas will be measured by volume, the estimated average annual volume of project natural gas is (using the estimates notified by the Commissioner):


  Estimated total volume of project natural gas  
  Estimated operating life  


9(7)    
For an operation in which natural gas will be measured by mass, the estimated average annual mass of project natural gas is (using the estimates notified by the Commissioner):


  Estimated total mass of project natural gas  
  Estimated operating life  


9(8)    
The expected operating life of the integrated operation is the period of years estimated as the operating life, as notified by the Commissioner, beginning with the production year.


 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.