Purpose

Information to provide testing guidance for digital service providers.

Last updated 15 January 2018

The SuperStream data and payment standards rollover message implementation guide (MIG) v1.0 was published in July 2013. Version 2.0 (v2.0) of the specification, constituting a major release of the Standard, was published in December 2015.

The purpose of this document is to provide testing guidance for digital service providers when undertaking conformance testing against the SuperStream Rollover MIG version 2.0.

The testing timetable will mirror the functional release schedule for the areas of functionality defined in the Rollover MIG v2.0:

  • Fund transactions  
    • Initiate Rollover Request transactions (IRR)
    • Initiate Rollover Error Response transactions (IRER)
    • Rollover Transaction Request (RTR)
    • Rollover Request Outcome Response (RTOR)
    • Version testing (version 1 & version 2) can be done in parallel
     
  • Government transactions  
    • Unclaimed Superannuation Money (USM)
    • Unclaimed Superannuation Money Outcome Response (USMOR)
    • Electronic Portability Form (EPF)
    • Version testing of EPF version 1 & version 2
    • Section 20C Notice to be added in a later version
    • Section 20C Notice Error Response to be added in a later version
     