MINERALS RESOURCE RENT TAX ACT 2012 (REPEALED)

CHAPTER 4 - SPECIALIST LIABILITY RULES  

PART 4-1 - MINING PROJECT INTERESTS  

Division 135 - Ending mining project interests  

Operative provisions  

SECTION 135-10   THE EFFECT OF RENEWING OR CHANGING PRODUCTION RIGHTS  

135-10(1)    
A change in, or a renewal of, the * production right to which a mining project interest relates does not cause the * termination day for the mining project interest to happen.

135-10(2)    
However, if the change in, or the renewal of, the * production right would otherwise result in the mining project interest covering an additional area:


(a) the * project area for the mining project interest does not include that additional area; and


(b) to avoid doubt, the additional area is the project area for another mining project interest.

Note:

The other mining project interest may be combined with the original mining project interest under Division 115 .



This information is provided by CCH Australia Limited Link opens in new window. View the disclaimer and notice of copyright.